📘 project management
Step-by-step solutions with LaTeX - clean, fast, and student-friendly.
Project Duration
1. **State the problem:** We have a project with activities A to H, each with durations and dependencies. We need to find:
- The total project duration
Project Crashing
1. **State the problem:** We have a project with activities A to G, each with normal and crashed times and costs. We need to find the overall project duration, crash costs per week
Project Crashing
1. **State the problem:** We have three activities A, B, and C with normal and crashed times and costs. We want to find the least desirable crashing candidate, the best activity to
Project Crashing
1. **State the problem:** We have a project with activities A to F, each with normal and crashed durations and costs. We want to shorten the project duration by 4 weeks at the lowe
Project Duration
1. **State the problem:** We have a project with activities A to J, each with durations and dependencies. We need to find the overall project duration, earliest and latest start/fi
Pert Chart
1. **Problem Statement:**
We have a set of tasks with durations and predecessor dependencies. We want to draw a PERT chart, which is a directed acyclic graph (DAG) representing tas
Project Management
1. **Problem Statement:**
We have multiple project management questions involving critical path method (CPM), project duration, slack time, and impact of changes on project schedul
Aoa Critical Path
1. **Problem Statement:**
Find the AOA network, critical path, event slacks, critical path to event D, critical path probability of completion in 14 days, and the effect of CD acti
Project Completion
1. **State the problem:**
We have a project with multiple jobs and their time estimates: optimistic ($t_0$), most likely ($t_m$), and pessimistic ($t_p$). We need to draw the proje
Project Management
1. The problem involves identifying the process that defines and controls what is or is not included in a project.
Answer: a. Project Scope Management
Critical Path
1. **State the problem:** We need to find the critical path in a project network given tasks, their predecessors, and durations.
2. **List tasks and durations:**
Project Value
1. **Determine the Earned Value (EV):**
The Earned Value is the value of work actually performed expressed in terms of the budget assigned to that work.
Project Activities
1. The problem states there is a small project composed of seven activities, each with a specified time duration.
2. To analyze the project times, list out all activity durations c