Pert Chart
1. **Problem Statement:**
We have a set of tasks with durations and predecessor dependencies. We want to draw a PERT chart, which is a directed acyclic graph (DAG) representing tasks as nodes and dependencies as edges.
2. **Understanding PERT Chart:**
- Each task is a node.
- Directed edges go from predecessor tasks to dependent tasks.
- Duration is a weight on each node.
- The graph must be acyclic.
3. **Tasks and Dependencies:**
- A (Requirement Analysis): duration 5, no predecessor.
- B (Systems Design): duration 15, predecessor A.
- C (Programming): duration 25, predecessor B.
- D (Telecoms): duration 15, predecessor B.
- E (Hardware Installation): duration 30, predecessor B.
- F (Integration): duration 10, predecessors C and D.
- G (System Testing): duration 10, predecessors E and F.
- H (Training/Support): duration 5, predecessor G.
- I (Handover and Go-Live): duration 5, predecessor H.
4. **Constructing the PERT Chart:**
- Start with node A.
- Draw an arrow from A to B.
- From B, draw arrows to C, D, and E.
- From C and D, draw arrows to F.
- From E and F, draw arrows to G.
- From G, draw an arrow to H.
- From H, draw an arrow to I.
5. **Summary:**
The PERT chart is a DAG with nodes A through I connected by edges representing dependencies as described.
Final answer: The PERT chart is constructed as above with nodes and directed edges representing task dependencies and durations.