Project Management
1. The problem involves identifying the process that defines and controls what is or is not included in a project.
Answer: a. Project Scope Management
2. Given: Project duration = 100 days, Budget = 10000, Days passed = 50, Amount spent = 7000, Work completed = 60%.
Earned Value (EV) is the value of work actually performed expressed in terms of the approved budget.
$$EV = \text{Percent Complete} \times \text{Budget} = 0.60 \times 10000 = 6000$$
Answer: b. 6000
3. Planned Value (PV) is the budgeted cost for work scheduled to be done by a certain time.
Since 50 days have passed out of 100 days, the planned work is 50%.
$$PV = \text{Percent Planned} \times \text{Budget} = 0.50 \times 10000 = 5000$$
Answer: c. 5000
4. Cost Variance (CV) is the difference between Earned Value and Actual Cost.
Actual Cost (AC) = 7000
$$CV = EV - AC = 6000 - 7000 = -1000$$
Answer: d. -1000
5. Two deliverables that form part of the Work Breakdown Structure (WBS) creation process are:
- Scope Baseline
- Project Scope Statement
Answer: b. Scope Baseline and c. Project Scope Statement
6. Using a previous completed project as a basis for a new project is called the Analogy approach.
Answer: c. Analogy approach
7. Tasks and durations:
- A: 4 days
- B (after A): 7 days
- C (after A): 5 days
- D (after B): 8 days
- E (after B, C): 9 days
- F (after D, E): 3 days
Paths:
- Path 1: A-B-D-F = 4 + 7 + 8 + 3 = 22 days
- Path 2: A-B-E-F = 4 + 7 + 9 + 3 = 23 days
- Path 3: A-C-E-F = 4 + 5 + 9 + 3 = 21 days
Critical path is the longest path: Path 2: A, B, E, F
Answer: b. Path 2: A, B, E, F
8. Causes of projects exceeding budget:
- Lack of resources
- Project not based on realistic cost estimations
Answer: a. Lack of resources and b. The project is not based on realistic cost estimations
9. Correct statements about six-sigma:
- Helps define the problem/opportunity, process, and customer requirements
- Is a tool useful for process improvements
Answer: c. Helps define the problem/opportunity, process, and customer requirements and d. Is a tool useful for process improvements
10. The second last phase in the Project Life Cycle is Monitoring and Controlling.
Answer: d. Monitoring and Controlling
11. Number of communication channels for 5 people (4 staff + Rachel):
$$\text{Channels} = \frac{n(n-1)}{2} = \frac{5 \times 4}{2} = 10$$
Answer: d. 10
12. Current Actual Cost is the amount spent so far.
Answer: a. 7000
13. Collaborative tools for project communication:
- Asana
- Telegram
- Google docs
Answer: a. Asana, c. Telegram, e. Google docs
14. Factor negatively impacting communication:
Answer: d. Geographical location