Project Value
1. **Determine the Earned Value (EV):**
The Earned Value is the value of work actually performed expressed in terms of the budget assigned to that work.
Given:
- Total Budget (BAC) = 10000
- Work completed = 60% = 0.6
Calculate EV:
$$EV = BAC \times \text{Work completed} = 10000 \times 0.6 = 6000$$
2. **Determine the Planned Value (PV):**
Planned Value is the budgeted cost for the work scheduled to be done by a certain time.
Given:
- Total Budget (BAC) = 10000
- Time passed = 50 days
- Total time = 100 days
Calculate PV:
$$PV = BAC \times \frac{\text{Time passed}}{\text{Total time}} = 10000 \times \frac{50}{100} = 5000$$
3. **Determine the Cost Variance (CV):**
Cost Variance is the difference between Earned Value and Actual Cost.
Given:
- Actual Cost (AC) = 7000
- Earned Value (EV) = 6000 (from step 1)
Calculate CV:
$$CV = EV - AC = 6000 - 7000 = -1000$$
**Final answers:**
- Earned Value = 6000
- Planned Value = 5000
- Cost Variance = -1000