Critical Path A4Eaff
1. **Problem Statement:**
You are tasked with managing the national roll-out of the SHIF programme. Using the given activities, durations, and precedence, you need to:
- Develop an Activity-on-Node (AON) network diagram.
- Calculate the Critical Path and total project duration.
- Compute slack (float) for each activity.
- Calculate expected durations using PERT formula.
- Calculate activity and path variances.
- Determine the probability of completing the project within a specified time.
- Identify crashable activities on the critical path.
2. **PERT Expected Duration Formula:**
$$T_E = \frac{a + 4m + b}{6}$$
where $a$ = optimistic time, $m$ = most likely time, $b$ = pessimistic time.
3. **Activity Variance Formula:**
$$\sigma^2 = \left(\frac{b - a}{6}\right)^2$$
4. **Calculate Expected Durations and Variances:**
| Activity | a | m | b | $T_E$ (weeks) | Variance $\sigma^2$ |
|---|---|---|---|---|---|
| A | 1 | 2 | 4 | $\frac{1 + 4(2) + 4}{6} = 2.17$ | $\left(\frac{4-1}{6}\right)^2 = 0.25$ |
| B | 6 | 10 | 16 | $\frac{6 + 4(10) + 16}{6} = 10.33$ | $\left(\frac{16-6}{6}\right)^2 = 2.78$ |
| C | 4 | 8 | 12 | $\frac{4 + 4(8) + 12}{6} = 8$ | $\left(\frac{12-4}{6}\right)^2 = 1.78$ |
| D | 3 | 6 | 10 | $\frac{3 + 4(6) + 10}{6} = 6.17$ | $\left(\frac{10-3}{6}\right)^2 = 1.36$ |
| E | 2 | 4 | 8 | $\frac{2 + 4(4) + 8}{6} = 4$ | $\left(\frac{8-2}{6}\right)^2 = 1$ |
| F | 4 | 8 | 12 | $8$ | $1.78$ |
| G | 6 | 10 | 14 | $\frac{6 + 4(10) + 14}{6} = 10$ | $\left(\frac{14-6}{6}\right)^2 = 1.78$ |
| H | 6 | 12 | 20 | $\frac{6 + 4(12) + 20}{6} = 12.67$ | $\left(\frac{20-6}{6}\right)^2 = 5.44$ |
| I | 3 | 6 | 10 | $6.17$ | $1.36$ |
| J | 2 | 4 | 8 | $4$ | $1$ |
| K | 4 | 8 | 12 | $8$ | $1.78$ |
| L | 2 | 4 | 6 | $4$ | $0.44$ |
5. **Construct Network and Calculate Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), and Slack:**
- Start with A (no predecessors): ES=0, EF=2.17
- B, C, D, E depend on A:
- B: ES=2.17, EF=12.5
- C: ES=2.17, EF=10.17
- D: ES=2.17, EF=8.34
- E: ES=2.17, EF=6.17
- F depends on B, C, E:
- ES = max(EF of B, C, E) = max(12.5, 10.17, 6.17) = 12.5
- EF = 12.5 + 8 = 20.5
- G depends on C, D:
- ES = max(10.17, 8.34) = 10.17
- EF = 10.17 + 10 = 20.17
- H depends on F, G:
- ES = max(20.5, 20.17) = 20.5
- EF = 20.5 + 12.67 = 33.17
- I depends on E, D:
- ES = max(6.17, 8.34) = 8.34
- EF = 8.34 + 6.17 = 14.51
- J depends on A, C:
- ES = max(2.17, 10.17) = 10.17
- EF = 10.17 + 4 = 14.17
- K depends on H, I, J:
- ES = max(33.17, 14.51, 14.17) = 33.17
- EF = 33.17 + 8 = 41.17
- L depends on K:
- ES = 41.17
- EF = 41.17 + 4 = 45.17
6. **Critical Path:**
The longest path is A -> B -> F -> H -> K -> L with total duration $45.17$ weeks.
7. **Slack Calculation:**
Slack = LS - ES or LF - EF. Activities on critical path have zero slack.
8. **Path Variance:**
Sum variances of activities on critical path:
$$0.25 + 2.78 + 1.78 + 5.44 + 1.78 + 0.44 = 12.47$$
9. **Probability of Completion by Time $T^*$:**
Calculate $Z$-score:
$$Z = \frac{T^* - T_{Epath}}{\sigma_{path}} = \frac{T^* - 45.17}{\sqrt{12.47}} = \frac{T^* - 45.17}{3.53}$$
Use standard normal tables to find probability.
10. **Crashable Activities on Critical Path:**
Activities with crash min duration less than normal duration on critical path:
- A (2 to 1 week)
- B (10 to 8 weeks)
- F (8 to 6 weeks)
- H (12 to 8 weeks)
- K (8 to 6 weeks)
- L (4 to 2 weeks)
These can be considered for crashing to reduce project duration.
**Final answers:**
- Critical Path: A-B-F-H-K-L
- Total Project Duration: 45.17 weeks
- Slack for non-critical activities calculated as above
- Expected durations and variances computed
- Probability formula for completion time provided
- Crashable activities identified